Palapye Water Treatment Works Expansion
PROFESSIONAL ENGINEERS & CONSULTANTS
LOCATION : Palapye Botswana
CLIENT : Water Utilities Corporation
CONTRACT VALUE : P386,841,038.82
COMPLETION EXPECTED/COMPLETION DATE : 24 February 2022
CONTRACT DURATION(MONTHS) : 30 months
SCOPE :
Design, Supply, Install, Construction and Commissioning of a new 40 million liters per day water Treatment Plant to increase the current capacity of the existing Plant from 18 million liters per day to 58 million liters per day
Build a Water Treatment Plant robust enough to handle high water flows and equivalent pressures on the new plant at Palapye Water Treatment Works and comply with water quality standard BOS 32:2015
Installation of all associated Electrical, Mechanical, Control and Instrumentation equipment, construction of six (6) staff housing, access road and a Control Room.